Plant Relocation (Midwest)
HETSCO served as the general contractor for the relocation and reconstruction of a 425 TPD air separation plant from Circleville, OH to Canton, OH and provided the following services:
-
Perlite Removal and Replacement
- Bracing and Supports for Cold Box (165'/300,000 lb.) and Argon Column (155'/150,000 lb.) Separation
-
Relocate Compressors, Motors, Piping Modules, Storage Tanks, Control Room, Switchgear Bldg., Cooling Tower, CW Pumps, PPU Tanks, Transformer, Generator, Vaporizers, Piping.
-
Provided Transportation for all Equipment
-
2 Dimensional Alignment and Erect Cold Box and Argon Column, Piping Modules, Compressors, and Equipment
-
Removal and replacement of all Column Structural Packing
-
Grouting of all equipment, pipe supports, tanks, etc.
-
Pressure Testing of Cold Box and Argon Column and all Associated Piping
-
Install all Tubing Trays and Pneumatic Tubing
-
Oxygen Cleaning of necessary Piping
-
NDT of Weld Requirements to ASME B31.3
-
Installed Piping Insulation
-
Painting of Cold Box and Argon Column, Piping, Supports, etc.